Light-duty overnight depot
$5,000–$15,000 per vehicle. Level 2 with managed charging inside an 8–12 hour dwell window. A 20-vehicle depot commonly lands $150,000–$350,000 installed.
Cost Guide · Fleet Depots · 2026
Depot cost isn’t a charger count — it’s dwell windows, duty cycles, and the site’s power ceiling. Real numbers and the sequencing that keeps vehicle deliveries from arriving before the power does.
The Numbers
Installed totals. The per-vehicle number is the honest metric — port counts follow from dwell windows, not fleet size.
$5,000–$15,000 per vehicle. Level 2 with managed charging inside an 8–12 hour dwell window. A 20-vehicle depot commonly lands $150,000–$350,000 installed.
$15,000–$40,000 per vehicle. Level 2 backbone plus shared DC fast positions for quick turnarounds and route exceptions.
$60,000–$150,000+ per DC position. High-power charging with dedicated utility infrastructure; multi-position sites share gear and improve per-position economics.
$50,000–$500,000+ and months of lead time. The swing item that defines both budget and schedule — confirm it before anything else is ordered.
$200–$1,000 per port per year plus demand charges — which managed charging exists to control. The software decision is an operating-cost decision.
30C (up to $100,000/port) + make-ready + fleet grants, and in CA/WA/OR, clean-fuel credits that pay revenue per kWh for the life of the program.
The Sequencing Rule
The most expensive failure in fleet electrification is a parking lot of delivered EVs waiting on a transformer. The fix is running the utility application and make-ready funding in parallel with vehicle procurement — not after it. Faith Energy’s depot work starts with the power question: real route data, real dwell windows, a load-managed design, and the utility application filed before the first vehicle PO.
Start with the power questionStraight Answers
Next Step
Vehicle list, dwell windows, and the site address — our engineers return a load-managed design, a real budget, and the utility timeline your vehicle orders should key off.